Approvals & paperwork

Waiting for power

Three months, many contractors, and a pole that looked like it had power

30 Sept 2026 · Bharath · updated 13 Oct 2026

Resolved. There is power on the plot as of 13 October 2026 — a single phase, 3 kW temporary connection. Everything below the line marked "It arrived" was written on 30 September, while we still had nothing, and has been left as it was. The ending is at the bottom.

It took one day to find water three hundred and twenty-five feet under this plot. It has now taken nearly three months to get a wire to it, and we still do not have one.

That sentence is the most honest summary of house-building we have written so far. The physical work has been the easy part. Everything that has genuinely cost us time has been paper.

Why a temporary connection matters more than it sounds

It is tempting to treat electricity as something you sort out near the end, along with the light fittings. It is not. A construction site needs power from more or less the first day, and for this house in particular:

  • The borewell pump. We have water at 310 feet. Without power we cannot lift a drop of it. A borewell without a pump is an expensive hole that you own.
  • Compaction. Rammed earth is built by compacting each lift, and doing that at any pace means pneumatic rammers, which means a compressor, which means real power. Hand ramming works — it is how this was done for centuries — but it is dramatically slower, and slower means more months of everything else.
  • Mixing. Getting a consistent earth mix by shovel across a whole house is not realistic.
  • The ordinary things. Cutting, drilling, welding, lighting when work runs past dusk, charging everything.

The alternative to a connection is a diesel generator, and we could run one. But it is expensive per hour, it is loud, and there is an irony in it we would rather avoid: this is a house being built partly because earth barely costs the planet anything to turn into a wall. Burning diesel for a year to compact it undoes a respectable share of the point.

What actually happened

We started chasing this the same week the borewell was drilled, in early July.

Since then we have been through contractor after contractor across Bengaluru — the people whose entire business is walking applications like ours through the distribution company. Some looked at it and declined immediately. Some took the details, went quiet, and came back weeks later to say it could not be done. A couple were confident right up until they were not.

Nearly all of them failed. One, finally, has taken it on and promised a connection by the second week of October.

We will believe it when the meter is on the pole.

The reason we were given

Every one of them came back with the same explanation: a restriction on new connections for properties above 1,200 square feet. Under that size, we were told, this is routine. Above it, a new connection runs into rules that most of them either could not navigate or did not think worth their time.

A caveat, stated plainly. We have not yet seen this rule in writing. What we have is the same answer from a lot of different people who do this for a living, which is evidence of something but is not the same as having read the clause. We are still trying to get the actual regulation in front of us, and we will update this entry when we do. If you know the specific provision, we would genuinely like to hear from you — and if we have it wrong, we would like to know that even more.

What we can say with confidence is the lived version: if your plot is on the larger side, do not assume a construction power connection is a formality.

What we would do differently

Start this before you start anything else.

We began the process in the same week as the drilling, which felt early and was not. If we were doing it again, the application for a temporary connection would go in before the borewell, before the soil test, before anything that happens on the ground — because those things take days, and this one takes months, and there is no reason they cannot run in parallel.

That is the actual lesson here, and it is not about electricity. It is that the critical path through a house is rarely the part you are worrying about. We spent our attention on soil and water, which were resolved in a day each. The thing quietly eating the calendar was a connection nobody thinks to plan for.

Where this stands

Started chasingEarly July 2026
Contractors approachedMany; almost all unable to proceed
Current positionOne contractor engaged, connection promised second week of October
Blocker, as reported to usRestriction on new connections above 1,200 sq ft — unverified
WaterAvailable, and unreachable without a pump

It arrived

13 October 2026. The contractor delivered, in the week he said he would.

We had written "we will believe it when the meter is on the pole", so it is only fair to record that the meter is on the pole. After three months of being told this could not be done, one person took it on and did it inside his own estimate. The difficulty was never that the connection was impossible. It was finding someone willing to work the problem.

What we have is a single phase, 3 kW temporary connection — enough to light the site, run hand tools, charge everything, and lift water once a pump goes in.

The cable we did not budget for

And then, immediately, the first surprise of the new phase.

The plan was straightforward. There is a pole near the site; the temporary shed sits about 120 feet from it; we budgeted cable for 120 feet and thought no more about it.

The pole did not have supply. It is standing there, it looks exactly like a pole that carries power, and it does not. The nearest point that actually did was another 120 feet further on — so the run doubled, and we bought cable twice.

It is a small thing and it was not a disaster. But it is a very good example of the shape these surprises take: not a catastrophe, just a quiet doubling of something you had already counted and closed the book on. Nobody was at fault. Nobody could reasonably have known without checking, and we did not think to check, because why would a pole not have power in it.

If you take one practical thing from this entry, take that one. Before you measure your cable run, confirm which pole actually carries supply — not which pole is nearest.

The broader version is the one we keep relearning: a construction budget is not a list of known costs. It is a list of known costs plus an allowance for being wrong about them in ways you could not have predicted. We are building in that allowance from here on, deliberately, rather than being surprised by it each time.

What it does not solve

Three kilowatts, single phase, lights a site and runs tools. Whether it will run a compressor for pneumatic ramming is the next question, and we suspect the answer is no — that is a heavier load and often a three phase one.

So the compaction question is still open. It will be a larger sanctioned load, or three phase, or a compressor on a generator used only on the days we are actually placing earth. We will work that out when the wall design is settled, and it will get its own entry.

Where this ended up

Started chasingEarly July 2026
Energised13 October 2026
ElapsedA little over three months
What we gotSingle phase, 3 kW, temporary
Contractors approachedMany; one succeeded
Blocker, as reported to usRestriction on new connections above 1,200 sq ft — still unverified
Unplanned costCable run doubled, 120 ft to 240 ft

Next on the list: lowering a camera into the borewell, to see the three water sources and confirm the depths before we choose a pump. That will be the next entry.